TMO10048492_TMO Document entitled _Status Report Updated 18 June 2013) regarding Status report at April 2013.pdf [pdf]
… TMO10048492_TMO Document entitled _Status Report Updated 18 June 2013) regarding Status report at … stage with the intention of delivering the construction phase on confirmation of a formal appointment. Whilst a …
Published on:
Transcript-of-opening-statements-5-June.pdf [pdf]
Published on:
KIN00000465_Al-Futtaim Exova - Fire Performance Testing of an External Cladding System BS 8414-1_2015 + A1_2017 - Kooltherm K15 - Report No. DLR1453 Rev.0.pdf [pdf]
… Performance Testing of an External Cladding System BS 8414-1_2015 + A1_2017 - Kooltherm K15 - Report No. DLR1453 Rev.0.pdf KIN00000465_Al-Futtaim Exova - …
Published on:
NHS00000004_Exhibit LP_1.2 - Recovery Management Protocol.pdf [pdf]
… NHS00000004_Exhibit LP_1.2 - Recovery Management Protocol.pdf NHS00000004_Exhibit … The Recovery process usually begins during the Response phase, which can be defined as the actions taken to deal … Group (SCG) I London Local Authority 1 Gold (LLAG) Reporting and information flow Recovery Coordinating Group …
Published on:
LFB00067838_Exhibit GR_46 - End of Year Monitoring of Commitments in the London Safety Plan and Key Projects for 2013_14 - FEP 2260.pdf [pdf]
… in the London Safety Plan and Key Projects for 2013_14 - FEP 2260.pdf LFB00067838_Exhibit GR_46 - End of Year … of Strategy and Performance FEP 2260 Public Summary This report provides the 2013/14 end of year monitoring position … reporting an amber status, 11. Construction is in two phases, phase I started at Orpington temporary and Mitcham …
Published on:
Transcript 21 October 2021.pdf [pdf]
Published on:
CLG00030869_Letter from Sir David Amess MP to Stephen Williams MP dated 19 March 2015 re BRAC Research Reports Relating to Fire.pdf [pdf]
… from Sir David Amess MP to Stephen Williams MP dated 19 March 2015 re BRAC Research Reports Relating to Fire.pdf CLG00030869_Letter from Sir … and that it is necessary to move beyond the testing phase and implement them more widely. The report considers …
Published on:
Expert-Evidence-21-November-2018.odt [odt]
… Expert-Evidence-21-November-2018.odt Expert-Evidence-21-November-2018.odt 1 … have provided to the inquiry a preliminary or 21 interim Phase 1 report dated 2 April 2018. I'll just 22 give the reference …
Published on:
Endnote 54 to the MHCLG Building Safety Timeline 26.10.18 and Endnote 17 to the Position Statement -Independent Review of Building Regs CLG10003161.pdf [pdf]
… Endnote 54 to the MHCLG Building Safety Timeline 26.10.18 and Endnote 17 to the Position Statement -Independent … Review of Building Regulations and Fire Safety Interim Report December 2017 Dame Judith Hackitt DBE FREng Cm 9551 … so far, the proposed direction of travel for the next phase of work and the rationale for that. It also identifies …
Published on:
Endnote 54 to the MHCLG Building Safety Timeline 26.10.18 and Endnote 17 to the Position Statement -Independent Review CLG10003161.pdf [pdf]
… Endnote 54 to the MHCLG Building Safety Timeline 26.10.18 and Endnote 17 to the Position Statement -Independent … Review of Building Regulations and Fire Safety Interim Report December 2017 Dame Judith Hackitt DBE FREng Cm 9551 … so far, the proposed direction of travel for the next phase of work and the rationale for that. It also identifies …
Published on:
G4 Closing Submission INQ00000569.pdf [pdf]
… Closing Submission INQ00000569.pdf GRENFELL TOWER INQUIRY PHASE 1 CLOSING STATEMENT ON BEHALF OF BSR REPRESENTED BY BHATT … ([2009] EWHC 76 (Admin)) [2009] 3 All ER 150 §73. See Report of the Azelle Rodney Inquiry, Chaired by Sir …
Published on:
Expert-Evidence-29-November-2018.odt [odt]
… Expert-Evidence-29-November-2018.odt Expert-Evidence-29-November-2018.odt 1 Thursday, 29 … presentation 13 setting out the work that has gone into his Phase 1 14 report, which has been circulated and published. 15 The …
Published on:
Appendix C.1 Transcript 30 January 2020.pdf [pdf]
Published on:
Transcript 30 January 2020.pdf [pdf]
Published on:
ARC00000743_2019.12.20 Arconic Opening Submission.pdf [pdf]
… ARC00000743_2019.12.20 Arconic Opening Submission.pdf ARC00000743_2019.12.20 Arconic Opening Submission.pdf Grenfell Tower … in mind that some of the findings may, as explained in Chapter 21 of the Phase 1 report relating to the cause and …
Published on:
Appendix D.3 BSR Team 2 written submissions and combined bundle of docs referred to.pdf [pdf]
… not be sending files to the CPS until the latter part of 2021, citing the need to wait for the conclusion of the … not be sending files to the CPS until the latter part of 2021, citing the need to wait for the conclusion of the … not be sending files to the CPS until the latter part of 2021, citing the need to wait for the conclusion of the …
Published on:
Transcript 28 October 2021.pdf [pdf]
… Transcript 28 October 2021.pdf Transcript 28 October 2021.pdf GRENFELL TOWER INQUIRY Day 194 October 28, 2021 Opus 2 - Official Court Reporters Phone: 020 3008 5900 Email: [email protected] … directly from the matters which were 17 reported on in the Phase 1 report and further examined 18 in the course of …
Published on:
BRE00027419_BRE and NHBC Fire performance of new residential buildings_2.pdf [pdf]
… forms of construction, by utilising non Ioadbearin9 masonry cladding systems for instance of a timber frame building … for the direct application of most finishes and proprietary cladding systemsI/I Tongue and groove Furring strips …
Published on:
BRE00027419_BRE and NHBC Fire performance of new residential buildings_3.pdf [pdf]
… forms of construction, by utilising non Ioadbearin9 masonry cladding systems for instance of a timber frame building … for the direct application of most finishes and proprietary cladding systemsI/I Tongue and groove Furring strips …
Published on: